% Completion column not working properly
VL0001
✭
Hello,
Any guesses why my % completion column isnt working correctly? There are no formulas for sumchildren etc. Its doing this automatically based on indents/outdents and for some odd reason the total project % complete is only considering task 1 and none of the others.
Something i am doing wrong?
Best Answer
-
Do you have dates entered in all of the sub-tasks?
Answers
-
Do you have dates entered in all of the sub-tasks?
-
Hmm i did, i changed some numbers and it worked now, i think task 1 had so much weight on it that little changes on other tasks didn't change the overall project completion %.
Thanks!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives