% Completion column not working properly
Options
![VL0001](https://us.v-cdn.net/6031209/uploads/defaultavatar/nWRMFRX6I99I6.jpg)
VL0001
✭
Hello,
Any guesses why my % completion column isnt working correctly? There are no formulas for sumchildren etc. Its doing this automatically based on indents/outdents and for some odd reason the total project % complete is only considering task 1 and none of the others.
Something i am doing wrong?
Best Answer
-
Do you have dates entered in all of the sub-tasks?
Answers
-
Do you have dates entered in all of the sub-tasks?
-
Hmm i did, i changed some numbers and it worked now, i think task 1 had so much weight on it that little changes on other tasks didn't change the overall project completion %.
Thanks!