Start dates in Gantt chart later than predecessor finish

enzo_vaire
enzo_vaire ✭✭
edited 07/10/24 in Smartsheet Basics

Hi,

I hope I am doing something wrong and this is not a fundamental 'feature' of Smartsheet….

I have a project plan with dependencies. I want to make sure that if a task is not started when the expected start date is reached (for whatever reason) the start date is updated to 'today'. This is not just to do with predecessors, because the engineer might be working on another project at the same time, or they might be ill, or on vacation, or whatever other reason.

I don't seem to be able to do this - is there a way to? I tried with automations, but I noticed I can't change the start date through an automation - the start date is completely dependent on predecessors.

Along the same lines, I don't seem to be able to update the finish date of the predecessor, to indicate late tasks.

Am I doing something wrong….?

All the best,

Enzo

Answers