Sort rows in timeline view
Hello,
I would like to sort the rows in timeline view. Current situation is my "planning" phase is at the bottom of the time line view, even though it has date ranges that are less than the subsequent phases. Ideally I would like to sort on "Phase" then on "Complete Date" but don't see anyway to do this. I also tried adding a "1-" "2-" in front of the phases to see if I could trick Smartsheet to ordering the rows in timeline properly, but that didn't work. Something in my grid view is forcing the planning section to go to the bottom. Essentially , I would like to get the "planning" phase below to the top row. Another piece of info is the "Planning" phase is the first section in grid view. Thanks!
Answers
-
I may have solved it - my Phase is called "Planning" but my first line of the planning section was also called "Planning." I changed this to "Systems" and it seemed to have fixed it. Maybe Smartsheet didn't like the redundant labeling?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives