Duration and start and end dates calculated by the predecessors
Hello,
I'm putting my predecessors separated by commas and I'd like to understand why the start date, end date and duration columns aren't being calculated automatically?
I'd also like to know how to set dates, as is possible in MS project?
I want to set dates and not necessarily have fixed intervals, they need to vary according to the dates of my predecessors, but in Smartsheet it doesn't work.
Answers
-
Right click one of the column > select 'Edit Project Settings' > Enable 'Dependencies enabled' > OK
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.1K Get Help
- 351 Global Discussions
- 198 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 135 Brandfolder
- 127 Just for fun
- 128 Community Job Board
- 443 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 284 Events
- 36 Webinars
- 7.3K Forum Archives