Duration and start and end dates calculated by the predecessors
Hello,
I'm putting my predecessors separated by commas and I'd like to understand why the start date, end date and duration columns aren't being calculated automatically?
I'd also like to know how to set dates, as is possible in MS project?
I want to set dates and not necessarily have fixed intervals, they need to vary according to the dates of my predecessors, but in Smartsheet it doesn't work.
Answers
-
Right click one of the column > select 'Edit Project Settings' > Enable 'Dependencies enabled' > OK
Leroy Noriega | Smartsheet SME | Independent Smartsheet Consultant
Core App, Project Management and System Administrator Certified🏅
E: leroy.noriega@yahoo.com | Linkedin Profile
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.7K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 468 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 64 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives