I am trying to export my SS project schedule and import into MS Project but Project is changing the start/end dates. I cannot figure out why this is happening. Please help!
Answers
-
There are many ways to update the actual start and finish dates in Ms Project, try the following.
- Select the Gant Chart view (View Gant chart) and the table is the Entry table (Table Entry) Select the task you want to update in the Task name field.
- Then select the Task Tab and select the Schedule group, click Update task.
- The Update Tasks dialog box appears, declare the Start & Finish dates for the Actual section and click OK.Entering the actual start or finish date for a task will change the execution time of the task, however, the planned date (baseline) is not affected and therefore it will create a discrepancy between the actual execution and the plan (Baseline).
-
Thanks but this is on import. It changed every single date in my project plan from Smartsheet.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.1K Get Help
- 444 Global Discussions
- 142 Industry Talk
- 472 Announcements
- 5K Ideas & Feature Requests
- 83 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 489 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives