% Allocation Automatically Populate 100%

Good morning,
We noticed yesterday that if we put in a new task in one of our sheets that has a % Allocation column, that column will automatically populate at 100%. We also found that if we have a current sheet with that column and change a duration or date, the applicable cell in the % Allocation will change from empty/blank to 100%.
Was this part of some other EAP or production roll out?
Answers
-
This was rolled out at the end of Aug. I tried to get ahead of it as this a major issue. Support said to create an product idea for their Roadmap.
Here is that request - please post there as well:
Request to be able to turn off default of 100% allocation โ Smartsheet Community
We are also routing these to our sales reps as this causing major disruption for RM