What happened to my critical path?!
Good morning Ss Community!
I found some great answers, especially to this question: Why don't I see the critical path? — Smartsheet Community so I have already tried some of those suggestions:
* sort by Start Date for chronological list of tasks helped the view but didn't fix my issue (see below for details)
* task spans the entire project that should be broken into parent/child tasks until that task is no longer on the critical path — That task was intended as a placeholder or title so I'm not sure how best to break up that task; maybe I just need to change its level until I can delete it? Also, Feel free make any other suggestions that could improve this tracker.
The issue: The last time I was in Ss, I had a small critical path with only a few tasks (just enough to make sure I was doing it right) but when I went in today to fill in gaps, that critical path has disappeared and the today's critical path contains completely different tasks. I assume this is due to new tasks being entered with dependencies that did not connect to what I had previously; fine. How do I rebuild the critical path? Is it possible to lock the path?
The attachment is zoomed in to show as much of the project time as possibe; unfortunately, it makes the indiviual tasks illegible.
Any guidance is appreciated
Thanks,
Jessie D (London ON)
Best Answer
-
The picture is very grainy. Here's what I would do to test a few hypotheses:
Make a copy, ensure the decency column is enabled.
Zero the milestone durations.
Each change check if the critical path returns.
Hope this helps.
Best Regards,
Yvonne Smythe
Answers
-
Hi @JessieD - I would suggest making a copy, changing the levels, and reviewing the predecessor rules on the back end (if you haven’t already done so). 🙂
Best Regards,
Yvonne Smythe
-
Thanks @YveNigma !
Can you break that down for me a bit more? Do I need to review the predecessor rules each time I change a level?
I was confident that the issue lies with the predecessor rules but I wasn't sure how to proceed. Thanks again :)
-
The picture is very grainy. Here's what I would do to test a few hypotheses:
Make a copy, ensure the decency column is enabled.
Zero the milestone durations.
Each change check if the critical path returns.
Hope this helps.
Best Regards,
Yvonne Smythe
-
Thank you so much @YveNigma!!
You sent me on the right path, which showed me that the dependency/predecessors got lost when someone else was making edits.
Now to fix it up again 😐️
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 412 Global Discussions
- 221 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 461 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives