Updating Holidays
Charles Osborn
✭✭✭✭
So each year, I update the holiday calendar in the Admin section which helps with all new projects, but any project conituing into next year will not be updated. How do other admins handel this, do you go into each project sheet to update that? Thanks.
Answers
-
@Charles Osborn , it all depends on how your solution is setup & whether you're using Control Center or not.
In general though, you could setup a master holiday sheet in your "Admin section" and use cell linking or cross-sheet references to pull holiday information into each project sheet. This way, each project automatically reflects any updates made to the master holiday sheet without individual manual updates.
All the best, DWise.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives