I would like to use the baseline function within a gantt view but only rebaseline select row(s).
I would like to use the baseline function within a gantt view but only rebaseline select row(s). I use one Smartsheet for many projects, but only one of them needs a baseline at this time.
-
Baseline disappearing when exported in PDF/PNG.
I've discovered a bug where the baselines displayed on the Gantt chart disappear when exported to PDF or PNG. This is clearly a defect, and I hope for a swift fix.
-
One template with scroll down options for different timings of tasks
Dears, As we know making formulas in duration time is not possible, so I'm looking for other option to make life easy in below scenario: We have several production plants, producing different product types and using different packaging pritnters which has influence on overall project timing for new product introduciton. I…
-
Data Mesh doesn't allow start and end dates when predecessors are enabled
If the project aims to transfer data from one sheet to another, automation could be a viable solution. However, there is a requirement that both sheets must be identical in order to facilitate the data transfer. At present, there is no available option for field attribute mapping, which would allow us to perform mapping…
-
Formula help on RYG Balls for Baseline Variance
hello all I'm struggling with this because the variance is in Days. I did a basic IF statement where: if the Status = complete then Green, and "nested if" if the Variance was < -5 then Red else Yellow. It just turned complete things Green and everything else yellow, because the variance is in Days (eg. 1d or -2d not a read…
-
IFERROR and MATCH Formula not pulling in formation - Prodactive S-Curve
hello, i came across a Video by Prodactive about S-Curves in smartsheet and so far everything has been working exactly as expected with one major exception; the "Actual" baseline. From the video and the downloaded examples, i used the exact same formula and referenced my sheet name versus what he had in his example. But…
-
Baseline Varianz Meilensteine
Hallo zusammen, hat jemand eine Idee warum mir Meilensteine (Dauer 0) je nach Platzierung innerhalb einer Projektphase (Ende oder irgendwo; jedoch NICHT am Rand der Phase) mit unterschiedlichen Varianzen zur Baseline (1T/0) angegeben werden obwohl Datumsangaben Ende/Baseline-Ende jeweils gleich lauten? → Beispiel in Phase…
-
How to get project overall delay in days in Smartsheet with multiple sub-parent rows
Hi While we use the Baselines on the task level to see the delays per task, is there a way to grab the overall project delay in days and also show it in the Dashboard? I'm using multiple sub-rows (up to three levels) to host tasks into different workstreams. Example: TOP ROW [Level] Parent Row1 [Level 2] Task 1 [Level 3]…
-
How to get project overall delay in days in Smartsheet
Hi While we use the Baselines on the task level to see the delays per task, is there a way to grab the overall project delay in days and also show it in the Dashboard? Thanks for any prompt Regards /Marat
-
Using Smartsheet Baselines values
Is there a way to use a helper Column and Formula to turn a Smartsheet Baseline variance into a real number so I can get an average? OR is there a better way to baseline changes to end dates?
-
Baseline Duration and Predecessors
I'd like to create a column for Baseline Duration and Baseline Predecessors, along with the current Start and Finish Date columns, when I baseline a schedule. In the cases where new tasks are added/inserted, the baseline predecessors would have to automatically adjust for the new row number that the predecessor has now…
-
Undo Baseline
The feature to undo a baseline that was recently executed in error would be really helpful
-
Reset Baseline Not Appearing for Admin Users
We're having an issue where the Set/Reset Baseline buttons are not appearing for Admin users. Is this a known issue or is there a setting we need to change so these appear in the baselines popup? Thank you! Note: We have tested multiple browsers for this. Users with a license can see and use the baseline set/reset buttons,…
-
Target Date vs Baseline in Project Management Office template
The project plan in PMO template have Target Start Date and Target End Date which seem to serve the same purpose as the Baseline Start and Baseline Finish. Are they redundant or am i missing something?
-
Baseline Visual in Gantt or Timeline view?
Hello! We have baselines set up on our sheet. Is there a way to show the variance visually, in the Gantt or new Timeline view - or is it only visible in that column as a number? Thanks!
-
Keeping track of old baselines
Hi I want to know if there is a simple way of keeping a log of baselines, e.g. each time it is reset, the old baseline is logged, similar to version control. The idea is that at the end of a project (which underwent change control resulting in the timeline needing to be re-baselined) we will be able to review the changes…
-
Baseline new activities added to schedule
How do I baseline new activities added to my schedule without it impacting the baselines already established for activities that had been in the schedule? My schedule is being populated in phases so new activities will be added over time. If I reset the baselines already established for work that was in the plan already,…
-
Easily Set Baselines in WorkApps
In the current state, we cannot set baselines from WorkApps unless we set the desktop view to grid view. This is not an ideal experience. Don't really want the project schedule in Gantt view at all times. This may spark the need for a second enhancement request related to being able to switch views in WorkApps, which…
-
Auto set Baselines
Is there a way to configure smartsheet to automatically set baselines at certain milestones in a project? My thought with this is my project plan would automatically set a new baseline at 3 different milestones, I would end up with 3 sets of baseline date columns. This would easily allow me to go back on projects and see…
-
Record Baseline Date in Activity Log
I oftentimes need to know on what date I baselined my project schedule in Smartsheet, but the date doesn't seem to be recorded anywhere. It would be nice if either the Activity Log or Baseline window showed the date when the schedule was baelined.