I am working with a project timeline with dependencies. I have set up 2 additional date columns for late start and late finish where the late finish date is a formula for late start @row + duration. How can I set this up to calculate all the dependent late dates for start and finish?
For example, I have several activities that are dependent on the arrival date of a piece of equipment. I want to model how those dates change if the delivery date pushes out.