Hello everyone,
On Smartsheet, I have a workspace containing a series of sheets (one for each active project) where various resources are planned.
Both on Smartsheet and Resource Management, each resource has 8 hours/day available (i.e., 1 day = 8 hours).
If I schedule a resource on two different sheets, assigning it to two different activities planned for the same day, the sum of the planned hours exceeds 8 hours/day, and in Resource Management, I correctly see the overallocation (red bar at 100%).
Is there a way to generate an alert and/or a block directly on Smartsheet, for example through automation, in case a schedule causes resource overallocation?