Status Update Formula

Options

Hi team, I have lost one of my most favorite formulas as a project manager. Here's what I'm trying to accomplish:

If % Complete is 100% - select "Complete" for the status column.

If % Complete is between 1-99% - select "In Progress" for the status column.

If % Complete is 0% - select "Not Started" for the status column.

Thanks all!

Best Answer

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!