based in the example below, I have various assignment and activities that run parallel to various construction activities across construction stage.
How do i set smart sheet to prioritise predecessor?
Research: this behaviour is a known limitation in Smartsheet. Unlike MS Project or Primavera, Smartsheet does not automatically calculate duration for a single task purely from SS
and FF
predecessors. Here’s why and how to handle it:
Why It Didn’t Work
- Smartsheet calculates start/finish from either:
- Start + Duration + Predecessors
- Finish + Duration + Predecessors
- If you leave Duration blank, Smartsheet does not auto-calculate the time span based solely on
SS
and FF
. - It requires a duration unless the task is a parent row, because child tasks control the parent row's span.