Good afternoon community,
We are in the process of rolling out Control Center and Resource Management. I am curious how everyone is tracking their resource times, availability and allocation? For example, we are dedicating 35% of an FTE's time (outside of the PMO,) to project time. Currently, we are forecasting our task duration and for the "% allocation" inputting 35%.
This creates an allocation of 35% every day of the task duration for the resource. If a resource is assigned multiple tasks in a day then they will show as over allocated.
How is everyone handling their allocation and availability?