Hi community - ran into an issue I've never experienced before. Across all my clients, we use formulas to project dates (we've used durations/predecessors in the past, but it's not our preferred method).
If we look specifically at the "TEST - SD - Internal Scope Alignment Call" line, you can see the "Start Date" formula, nothing crazy, just adding 1 day to the previous complete date. In the main sheet, this is computing a date: 03/24/26.
However, in my report, it is not pulling in a date. It just shows there is a formula in the cell and its non-editable.
I've confirmed i'm sourcing from the correct sheet and pulling in the correct columns.
I have a rollup sheet that indexes the start and complete dates of specific tasks as well, Internal Scope Alignment Call being one of them. When it's a hard coded date, the index formula works; when it's a formula populated date, it's blank.
Can someone please explain why this is happening? And how to remedy? Or is this just a glitch?