Hello everyone,
I guess (or hope) some of you have used the PMO template that contain these 2 columns, and then it calculates the overall "Health" based on the delay.
However, I'm struggling with them and how to update them…
Here is the scenario:
- Let's say that I just created my project plan, so it is easy to set the Actual from/to dates and then copy values to Planned from/to dates.
- When adding lines (from scratch), I add the Actual from/to dates… Most likely, Planned dates will remain blank.
- When copying lines, I can update the Actual from/to dates, but (unless updated too) Planned dates will be wrong, as they have the original value (from the cell I copied it from).
- Conclusion: the Health calculation is not reliable…
Now, you may say "use the Baseline", but as far as I have read, I could not find the option to keep the original Baseline, and set up the baseline for new lines (only)…
Also, I understand that you need to manually trigger the Baseline for creation/update.
I was wondering if any of you had managed to "automate" any of these steps.
Thanks for your feedback.