Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Gantt Chart Due Date Flag / Milestone
Hi,
Is it possible to show a 'flag / milestone' as well as the duration bar on one line of data. I would like to have a due date associated with a task, as well as a duration. Such that I can see instantly how close I am to a due date.
Thanks
Comments
-
Hello,
You will not be able to display the duration within the taskbar but you can certainly display the percentage complete column to see how close you are to the due date. Then, you can select the End Date column to be displayed on the right of each taskbar in the Gantt like in the screenshot below.
To do this:
- Create and name a percentage column. Insert the percentage complete values in each row
- Click the Project Settings icon in the Gantt chart header. The Dependency settings form will open.
- Under Options, select the percentage complete column you just created.
- Click Timeline Display, Then under Display label For select End Date.
This will show in the taskbar of the Gantt how much of task has been completed and when the task is due. I hope this helps.
Kind Regards,
Pam
Smartsheet Technical Support Specialist
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives