Hi guys, any advise on how works with % completed vs planned % completed as smartsheets only has column for % completed?, has anyone achieved to make a similar column for planned %?
Hello,
You can create a new text/number column in your sheet and format it for percent. Details on formatting columns for percent can be found in our Formatting Options help article.
If you need planned percent complete to be calculated for you, you'll need to create a formula in Smartsheet that does this. You can find the complete list of functions here: https://help.smartsheet.com/functions
I am currently setting up an automation for people to get notified through their email, when they are prompted. But is there a way that they can reply in the email of a comment that will then go to the specific sheet. This way they do not have access to the sheet, but can just comment through email with updates?
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.