Sign in to join the conversation:
The posts in this section are historical and no longer monitored for accuracy. If this discussion interests you and you'd like to join in, please visit the active Community to post and engage.
We set up a new sheet based on the template: "4 Month Product Launch with Gantt"
However, when I update the launch date, none of the dates get updated in the sheet.
I just tested this by opening a new sheet created from 4 Month Project Launch with Gantt and when I changed the dates on row 3, all the dates under it changed as well. Did you delete any predecessor values or did you turn off dependencies? All the dates are linked together using predecessors so if you removed the values from the Predecessor column OR added custom start dates for tasks (which would delete the predecessor) then you wont see this functionality. If you do not see predecessors, try adding them back.