Cell-link: Duration and Start Date - End date isn't same
Hello Community people,
I have same duration and Start (date) in 2 sheets, which linking is set. But End date gets different. Dependency settings (Working Days and other items there) are exactly same.
Start . End . Duration
Original sheet 5/7/18 5/6/19 260d
Linked sheet 5/7/18 5/3/19 260d
This task does not have dependencies. Could someone tell me why and how I can set End date same?
Comments
-
Something is wrong on the original sheet. Without holidays, 260ds from 2018-05-07 is 2019-05-03, as shown on your linked sheet.
Can you post a screen shot of your Project Settings? The only thing I can think of is that there are holidays set.
Craig
-
Hi Craig, thank you for your help, and I apologize my very long delay.
In Source sheet End date is 5/14, but linked sheet has 5/11. Same start date, duration is 49d. No holiday is set.
Source sheet -
https://www.screencast.com/t/TtFYkqm891S
https://www.screencast.com/t/qSRuXbksWZ
Linked sheet -
https://www.screencast.com/t/GhVb9KfW
https://www.screencast.com/t/hEpuxsSHXXO
-
I am having the same issue and have already checked my project settings. Is there really no resolution on this since 2019?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.9K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives