Exclude weekends from a schedule
Louise
✭
I am using this for a project schedule and wanting to exclude weekends permanently.
I am using the start date and duration fields for this schedule but need to exclude weekends.
For example if a job starts on Wednesday and is a 5 day duration i need this to show as complete on Tuesday (as our trades don't work Sat/Sun)
Comments
-
Hi,
Here is the solution:
- Right-click on the duration column and click on "Edit column properties".
- Click "Project Settings"
- On the project settings screen click on "Edit" below the 'Working days' section.
- Set your working days.
*See screen shots below
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 495 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives