Equivalent of MS Project constraints in Smartsheet
Dear All,
Can someone tell me what is the equivalent of MS Project constraints in Smartsheet. I have been reading of using Lag time but wanted to know if there is another way of doing it the same.
Many thanks,
Taru
Comments
-
Hello Taru,
Er du Norsk?
Smartsheet has dependencies built right in. You can use these to achieve what you're after.
- You'll need some date columns in your sheet, so create Start Date and Finish Date columns (in Date format).
- Next click on the Gantt View in the toolbar to the left of your screen.
- When the Gantt appears, click on the Edit Project Setting gearwheel in the top left of the Gantt.
- You'll see that Smartsheet has already found your Date columns and assigned them within the Dependency Settings window.
- To enable Dependencies, check the Dependencies Enabled checkbox below this.
- If you don't already have Predecessors and Duration columns in your sheet, Smartsheet will automatically create and assign them for you.
Note: You'll also see a number of other project options that can be set on this screen, including % Complete, Working Days and Working Days. Feel free to set these now.
If you locate the Predecessors column in your sheet, it will behave in a similar way to MS Project, with the ability to free type dependencies (e.g. 2FS + 2d, 24 etc.) or set them via the pop-up dialogue that appears when you click on the edit icon in each cell.
Hope this was what you are after.
-
That's a big big weak point of smartsheet not to be able to have the ability to constrain dates like in microsoft project and primavera.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives