Calculating Total Duration from my project sheet
I am new to smartsheet and I am trying to SUM the number of days from the "Duration" Column. If I understand the Help files correctly, you can only use the SUM function in number fields?
If I use only Days in my "Duration" column, is there a way to SUM up a total at the bottom of my sheet?
Thanks in advance
Comments
-
Yes, but not in the same column. You can use Sum(Duration:Duration) assuming your duration column is called duration. This will sum the entire column. This will always update even when rows are added.
Note: You can't put the sum in the same column and have it automatically do all the rows because it would create a circular reference and try to add that sum to the total and you'd have an infinitely increasting number.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.3K Get Help
- 364 Global Discussions
- 199 Industry Talk
- 428 Announcements
- 4.4K Ideas & Feature Requests
- 136 Brandfolder
- 127 Just for fun
- 128 Community Job Board
- 445 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 283 Events
- 35 Webinars
- 7.3K Forum Archives