Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Overriding Non-Working Days
Most of our projects include M-F working dates, however at the end of each project there is often a conference or event which may take place over a weekend or other non-working day. I'd love to be able to override and enter tasks on weekends for these instances without turning the entire project into a 7-day work week project and accidentally having other tasks "pushed" onto a weekend by mistake. Is there a way to override?
Comments
-
I think the only way is to make the default a 7 days working week and make the 'normal' weekends exception.
-
Do you mean set the working week to 7 days but make all weekends (except for the weekend of the event) a non-working/holiday/vacation status?
That might work. Thanks!
-
Yes, that is what I mean. It is a bit basic workaround but it works.
-
If its only only a weekend here and there, you could do the following:
-Create a new task (row) for Sat and Sun (each row only scheduled on one day)
-Create a row above the two weekend rows.
-Indent the two weekend rows under the new row
Now you can collapse the two weekend rows under the parent row to give the impression of a single row but still have your weekend task.
-
- Elapsed time (lead with an e to indicate duration in elapsed time e.g. e3d, e5h, e3.5d, etc). A task with a duration in elapsed time ignores non-working time. The task will start and end in the amount of time specified regardless of working day length and non-working days in the sheet.
-
Adding the Sat and Sun rows indented gives the impression in the gantt view but the days total is only 1d for a Fri-Sun range instead of 3d.
-
Thanks "Crissy Nolen"
I'd tried it and it is working fine
-
Brilliant, thank you!
-
Thanks for solving this for me -- just the guidance I needed!
-
Crissy, hello.
I have a date and duration calculating problem where a task of 6 days duration is behaving in an odd manner when I try to use your prefix 'e' solution to "override" Sat and Sun as non-work days within Project Settings.
Grid and Calendar Views both show 7 days Duration instead of the specified/required 6 days, and Gantt View shows just 5 days.
Any thoughts as to what I may be doing wrong?
Any help appreciated!
-
Thank you for this, works perfectly
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives