Resources allocation / staffing at hourly granularity
Hi. we have the need for a tool that will allow us manage short & simple projects (hours/days) for our team. Something like Float.com. As we are using Smartsheet already, i'd prefer to find a solution that utilize SS, instead of bringing to the company another solution. But - I didn't find a way to work on an hourly basis here. any ideas/suggestions? Thanks, Doron
Tags:
Comments
-
Hi Doron,
You can create tasks with partial day duration (hours, minutes, even seconds) and create dependencies between them as you would with longer projects.
Information on dependencies can be found in the help center: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives