ability to "nudge" bars in gantt view

✭✭
edited 12/09/19 in Smartsheet Basics

Wouldn't it be nice, when laying out a project in gantt mode, to be able to just use the arrow keys to "nudge" the bars left and right in order to tweak the final details? Has anyone figured out how to do this?

Tags:

Comments

  • ✭✭✭✭✭✭

    Hi mkirchman,

    While you can't use the arrow keys to "nudge" them, you can certainly click and drag the taskbars or even resize them (by hovering over either end) to tweak the plan.

    Kind regards,

    Chris McKay