I have a question that I am embarrassed to ask. I thought that I would know the answer with no doubt . If you build a task that is dependent on the completion of a previous task with a Finish to Start relationship (very standard) and the previous task ends on April 9th (a Monday) shouldn't the next task (the dependent task) have a start date of April 10th? I have a task in that situation but, it begins on April 9th. I can add a lag day and force it to April 10th. But, that shouldn't be necessary. Am I correct or am I losing my mind? I don't have any other dependencies on the task.