Hey there, new to Smart Sheet and have a question.
I'm building gantt charts for some of our projects.
I’d like to be able to account for the amount of people that belong to a group/resource to properly scope the amount of time needed for each task.
For example, one task within the Gantt would be ‘Fabrication’ – I assign 10 hours for the Fabrication task. I assign the Fabrication Team under the Assigned To column. However lets say there are 2 fabricators, so the hours should plot at 5 hours opposed to the full 10.
Any insight would be greatly appreciated, thanks!