Rescheduling Remaining Work

mccormjx
mccormjx
edited 12/09/19 in Smartsheet Basics

If you are familiar with MS Project, you are aware of the Reschedule Remaining Work functionality.  Does this type of feature exist in Smartsheet?  If not, what is used to "push" out work not completed to determine the new end date?

Comments

  • HI, nothing in the system will do that other than manual intervention to eg increase the duration to the delayed task/s or if it hasnt started at all to move the start date back.  All manual I'm afraid.

    Mick