I am working on a schedule and have a row with no predecessor, however the "start date" won't let me manually change it. It keeps auto-correcting back to the same date that has been in it from the beginning.
Any thoughts?
Really agree with that first sentiment. If these limitations exist, at least there should be proposed solutions as pop-ups, or something. AI can write formulas (this has been useful)…maybe AI could suggest solutions to these types of issues.
Also - really appreciate the solution @RJosephWilson - using 0 as predecessor works. It also makes sense, but should not be necessary.
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…