I am wanting to put the gantt view of my project plan in a dashboard.
How do I go about doing this?
Hi,
You would use the report widget to show a report in Gantt view on the dashboard.
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant @ Get Done
Hi Andree,
Thanks for your response. My gantt chart is in a sheet, not a report though. If I created a separate report, it doesn't look right. Do I need to do this extra step to pull into report form?
Happy to help!
To show the Gantt in a Dashboard, you need to create a report of the sheet or sheets that you want to display. Unfortunately, there isn't another way to do it.
What is it that doesn't look right?
Got it! Thank you, Andree.
This is an old thread but hope still active. When you create a gantt in report format you loose all of the dependencies and there appears no way to display them. Any advice. I really want to see the gantt the way it is displayed in the sheet ie. with dependencies and critical path.
seems odd that smartsheet has not added this functionality. Gantt chart should be able to be displayed with dependancies.
I have set up a form with conditional logic to display the fields I want to display upon select criteria and that is working. However, at the beginning of the form I only want 2 fields to display and the rest to be hidden. Based on the below logic I thought the form would only show the first 2 fields selected but that is…
Hello, I am not sure i understand what the scheduler means in the data shuttle I have set up. Does the below mean that my scheduler will run every hour from 5 am to 8 pm each day? I need it to update often but not sure if this will do it or not. Thank you to those that are smarter than me :-)
I have requested for a snapshot, but I have not received the email yet. Any idea why and what do I need to do?