I am wanting to put the gantt view of my project plan in a dashboard.
How do I go about doing this?
Hi,
You would use the report widget to show a report in Gantt view on the dashboard.
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant @ Get Done
Hi Andree,
Thanks for your response. My gantt chart is in a sheet, not a report though. If I created a separate report, it doesn't look right. Do I need to do this extra step to pull into report form?
Happy to help!
To show the Gantt in a Dashboard, you need to create a report of the sheet or sheets that you want to display. Unfortunately, there isn't another way to do it.
What is it that doesn't look right?
Got it! Thank you, Andree.
This is an old thread but hope still active. When you create a gantt in report format you loose all of the dependencies and there appears no way to display them. Any advice. I really want to see the gantt the way it is displayed in the sheet ie. with dependencies and critical path.
seems odd that smartsheet has not added this functionality. Gantt chart should be able to be displayed with dependancies.
I am looking for a way to automate a cell so that when column A displays 9 'Days Open' (or between the values 0-14) the 'Req Age' will auto populate (or trigger) the ranges provided. Image below: I want the highlighted section to auto populate based on the value in 'Days Open'
Good morning, I haven't needed to do this is quit a while but I went to clean up the "Sheets" folder in my account and can no longer create a folder, sheet, or report in any area of that folder. The "Create" button at the top right takes me the templates page. This is what I am seeing vs what I can do within a workspace.…