New to Smartsheet,
trying to create a notification that would notify a person when due date is 3 days or fewer.
thanks for your help.
SGF
Set up a reminder. click on the little bell like symbol and you can set reminders. if you are an admin , you can set for more than one person.
is this a 1 time reminder? or will it automatically send a reminder anytime the task is 3 days until due?
thanks
The Reminders are checked early morning Pacific Time Zone. If they match the criterion, they will send. If you change the date to the future, it will fire again when it matches the criterion.
This is per row, so multiple Reminders might be sent on the same day for different rows.
The image above is misleading.
If there is a Date type column, you can set the Reminder to use that instead of a fixed date.
Clicking the on link will open a selection for various lead/lags from the given date.
Craig
Hi, if I add a new row above an existing row which has a predecessor, does Smartsheet automatically update the predecessor number ?
Solution is to have a paid subscription which we have but have lost the functionality of emailing attachments from Smarsheets. Has anyone else had this issue?
Hello- I have to constantly refresh my browser in Edge and Chrome as my shared workspaces go missing for clients. Sometimes when I refresh it works, other times it doesn't show half the clients or workspaces I have access too. Other times when refreshing data it doesn't work on my side, but will work for a co-worker. This…