When adding a resource (Assigned To) and the % allocation on a task line, with subtasks, why will it not take the allocation percentage?
What formula are you using in the parent row to add the Allocation %, or do you have dependencies enabled in the Gantt View settings?
Thanks for your reply. No formulas. Yes, dependencies are enabled. When I enter a number, it just disappears and doesn't stay in the cell. Any thoughts?
When dependencies are enabled, whatever columns are being used for those dependencies, the parent rows are automatically considered a "summary row" of the children rows. Changes cannot be made to those cells to include using formulas and/or manual entry. Here is a link that should help explain things a little better. It is the page the link in the screenshot below sends you to.
https://help.smartsheet.com/articles/765675-work-with-gantt-chart?frame=0&nav=1
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…