Allocation percentages not being added
When adding a resource (Assigned To) and the % allocation on a task line, with subtasks, why will it not take the allocation percentage?
Comments
-
What formula are you using in the parent row to add the Allocation %, or do you have dependencies enabled in the Gantt View settings?
-
Thanks for your reply. No formulas. Yes, dependencies are enabled. When I enter a number, it just disappears and doesn't stay in the cell. Any thoughts?
-
When dependencies are enabled, whatever columns are being used for those dependencies, the parent rows are automatically considered a "summary row" of the children rows. Changes cannot be made to those cells to include using formulas and/or manual entry. Here is a link that should help explain things a little better. It is the page the link in the screenshot below sends you to.
https://help.smartsheet.com/articles/765675-work-with-gantt-chart?frame=0&nav=1
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 439 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 67 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives