I'm creating a "summary schedule" report from the project schedule and would like to include a hyperlink to the full project schedule within the report for quick access. Any tips to offer on that?
Hi Royce,
You could either use the sheet name column in the report or add a row in the schedule sheet with the link and include that row in the report.
Would that work for you?
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant @ Get Done Consulting
I'm trying to create a graph chart that captures monthly count of records by divisions (Northeast, West and Central) that should be stacked with a legend displaying each by different color like a presented in Excel. When I attempt to duplicate the process in Smartsheet I receive the following results. In Excel, I created…
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…