Hi, we are planning a home construction project and are not sure of dates. Is there a way just show days without dates, and exclude Sat/Sun?
Hi,
You can plan out the project and only begin with using the duration column, but it will not show a Gantt chart (I think that´s what you're after?). You'll have to have start and end dates to be able to show the information on a Gantt chart.
Regarding the exclusion of Sat/Sun. You can set that up in the Project Settings - Dependency Settings in the Gantt view.
I hope this helps you!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Circling back to this….. Another year goes by and still no folder level sharing. Smartsheet developers don't listen to their clients. I have seen hundreds or posts and requests for this over the past 7-8 years. And still NOTHING!! This has been a huge issue for us as a company. As you can tell this is a sore spot for us…
Today a team member accidentally changed several rows by either deleting the data or the row itself. Do I download a snapshot of each one to restore? Some of them didn't seem to be too helpful. What is the protocol for restoring this information? I've only done this before with the help of a representative and it was…
I have my Smartsheet set to generate a document when a form is filled out. The document is a fillable PDF and when the document generates not all of the answers populate on the generated PDF. I have tried making the PDF again from scratch, I have tried copying and pasting the fields so I know they're the exact same…