Rollup percentage in project schedule template is not calculating correctly
I'm using the project template in smartsheet, in grid view. I've broken my project up in several phases, each phase a parent with child tasks. The Project % complete is coming out as 99% complete, but it is far from being that complete. Is there something I have to do to get this to calculate correctly, or do I have to manually do parent/child formulas? If so, I would of though that the project smartsheet template would of handled that.
Please note that if I start a project with or without the Project information (first 6 rows of the project detail) the % complete doesn't change.
Comments
-
I would suggest checking which columns are being used in your dependency settings first.
-
Hi Michele,
Great question! When using the % Completed column in the Project Settings, it calculates a weighted average. Since so many of your tasks do not have dates or a duration their weighting is zero. If you add expected dates, you'll see the % Complete update accordingly.
Let me know if this answers your question.
Paul Koetke
Upwork - Smartsheet Consultant
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives