My duration roll ups for child/parents are not working as expected. Can anyone advise of things I could try to resolve why only one parent has a duration total?
Hi Paul,
Start with checking your Project Settings (Right-click on any column and select Edit Project Settings).
Edit: You must have durations and dates for the parent to show the total duration.
Did that help?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I had the project settings on, but turning off and then back on worked!
thanks
Great!
Happy to help!
Andrée
I need a formula that says, if the "Complete?" box is checked, was the date in the Actual Completion column on (or before) the date in the Finish column.
I feel like this should be super simple but I am just not getting it right. Based on Frequency: Daily, weekly, monthly I want to change the next due date This will be calulated from Created column and +1, 7, 30 etc added. It works single instance =IF(Frequency@row = "Daily", Created@row + 1) but as soon as I try to write…
I have a sheet summary report on a dashboard and oftentimes the values will not update unless I go into the source sheet and manually save the updates. For example, the WEEK TIME OFF value often will not update week-to-week unless I go into that contact's sheet and save. I have tried adding a daily Chron automation…