My duration roll ups for child/parents are not working as expected. Can anyone advise of things I could try to resolve why only one parent has a duration total?
Hi Paul,
Start with checking your Project Settings (Right-click on any column and select Edit Project Settings).
Edit: You must have durations and dates for the parent to show the total duration.
Did that help?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I had the project settings on, but turning off and then back on worked!
thanks
Great!
Happy to help!
Andrée
I have a sheet where there are several different "Assigned To" columns and then a "Project Status" column. I need to create an employee workload report. Each report should only show that employee's assigned to tasks that are in their current status. For example: Deron's report should show the row Project Name and Project…
I know I'm going to kick myself when this gets resolved, but I'm having a bit of a brain fart right now. I'm trying to get the lowest non-blank value in a particular range (columns A-E). [A]@row=18, [B]@row=16, [C]@row, [D]@row, & [E]@row are all blank. All five rows are products of column formulas. Basically, there are a…
I am trying to have the Drop Dead column subtract 42 days from the Final Confirmation Date. I have the Drop Dead column setup as a Date Column and have tried doing this formula, but am getting an "Invalid Operation" error. Can anyone tell me what I am doing wrong? And thanks in advance.