My duration roll ups for child/parents are not working as expected. Can anyone advise of things I could try to resolve why only one parent has a duration total?
Hi Paul,
Start with checking your Project Settings (Right-click on any column and select Edit Project Settings).
Edit: You must have durations and dates for the parent to show the total duration.
Did that help?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I had the project settings on, but turning off and then back on worked!
thanks
Great!
Happy to help!
Andrée
I am trying to populate a column from Sheet A into Sheet B and Sheet C. My Lookup column for Sheet A is formatted as such so there is a ' in front to account for ones that have a leading 0 and some do not. Each ID should be 6 digits long. I made a helper column looking at this Dealer ID column to try and get rid of that…
am I able to separate this into multiple rows? in a new sheet? Desired Result -
I would like to parse out this data by creating a listing with a row for each person, for each project they appear on, for each month. I think this would only give me the groupings anyways, but this doesnt seem to even get me started - it popped up then people have disappeared.