My duration roll ups for child/parents are not working as expected. Can anyone advise of things I could try to resolve why only one parent has a duration total?
Hi Paul,
Start with checking your Project Settings (Right-click on any column and select Edit Project Settings).
Edit: You must have durations and dates for the parent to show the total duration.
Did that help?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I had the project settings on, but turning off and then back on worked!
thanks
Great!
Happy to help!
Andrée
Hey, Is anyone else facing this issue in the approval notifications sent through smartsheet
I have a sheet with a list of customers in one column, and then the following columns are City, Monday, Tuesday, Wednesday, Thursday, Friday. I need help with a formula that I can put in my sheet summary so that if the customer column says Staples (It can say this in multiple rows) that it will tell me the total package…
Hi Smartsheet community, I've always tried to answer questions but this is my first time posting. So I have formula =IF([Project Status]@row = "Complete", 1, 0) set up in the "Complete Check - Hide column" to check the box when the project status is marked complete. The project status column is tied to several other sheets…