Sign in to join the conversation:
My duration roll ups for child/parents are not working as expected. Can anyone advise of things I could try to resolve why only one parent has a duration total?
Hi Paul,
Start with checking your Project Settings (Right-click on any column and select Edit Project Settings).
Edit: You must have durations and dates for the parent to show the total duration.
Did that help?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I had the project settings on, but turning off and then back on worked!
thanks
Great!
Happy to help!
Andrée
Smartsheet Community - I AM STUMPED!! I am trying to do a crosssheet SUMIFS formula with 1 Column and 2 Rows of Data. I need to sum across {Weeks 1 to 104} Column to match : {Helper Column} = Baseline@row Vertical Rows {Month} needs to match Month@row, and Row {Year} needs to match Year@row I have tried SUMIFS, JOIN,…
Hello I am looking to create a Smartsheet formula that returns the following result: Column A "Created Date" - this column type is a Created date and show results with date and time Column B "Received Date" - this column would round up the "Created Date" and just show date, no time. If the "Created Date" was after 2:00pm…
Cant figure out why this is not working. It comes back NO MATCH. I have changed it to true and to 1. Nothing works. HELP