Sign in to join the conversation:
Hi, which formula can I use to calculate the expected Progress (depending on the current date)?
Thanks
Could you give more details and share some screenshots?
Hi Paul,
I have the Start Date, End Date, Duration (days) and the Progress given by each responsible. From this Information I would like to calculate the expected Progress, how shall the Project must be going on an specific date.
For example:
I have a Task with 10 days as Duration. by the second day the Progress completed is 20% (that means is running accordingly to plan) and by the third day, the Progress is the same. That means that by the third day the Project has already a delay.
So I would like to know which formula can I use to find out this expected or planned Progress and then I can be able to make a comparison against Progress completed and create alerts if neccesary.
Thanks.
If you create a [Projected % Complete] column, you can enter this formula into it...
=(TODAY() - [Start Date]@row) / ([Scheduled End Date]@row- [Start Date]@row)
This will give you how far into the scheduled time you are for whatever today's date is. You can then build your alerts off of whether your actual % complete is less than, greater than, or equal to where you should be (projected % complete).
To show the projected finish date based off of the current progress and the start date, create a date type column [Projected End Date] and insert this formula...
=[Start Date]@row+ ((((TODAY() - [Start Date]@row) / ([Scheduled End Date]@row - [Start Date]@row)) - [Actual % Complete]@row) * ([Scheduled End Date]@row - [Start Date]@row)) + ([Scheduled End Date]@row - [Start Date]@row)
Thank you!
I have a similar request: I would like to see how the projected end date of a task will impact the overall projected end date of the project taking the predecessor relationships into account. Any ideas on how to do that with a function or in a dashboard?
Column with multiple drop down options (cities). Some submissions have one city specified, some multiple. Followed by four optional columns (Brand 1, Brand 2, Brand 3, Brand 4). Not all entries have four brand entries, some 1, some 2, etc. I would like to have a count of the number of brands (cells that are NOT blank) per…
HI All, I have a formula that i have got working - only issue i have is I have run out of cross reference "space" and cannot add my last spring to complete my function is there anther way to do this Source sheet OR date UP date Site Target sheet Required date Updated Date Site i need to return source sheet UP date, when OR…
I want to pull through the task name in one sheet where the check box at row is checked into another target sheet. This is what I though the formula would be but I get #UNPARSEABLE as the error. =INDEX(COLLECT({Task name}, {Stage check box}@row , 1)) Um, help please?