Sign in to join the conversation:
Hi, which formula can I use to calculate the expected Progress (depending on the current date)?
Thanks
Could you give more details and share some screenshots?
Hi Paul,
I have the Start Date, End Date, Duration (days) and the Progress given by each responsible. From this Information I would like to calculate the expected Progress, how shall the Project must be going on an specific date.
For example:
I have a Task with 10 days as Duration. by the second day the Progress completed is 20% (that means is running accordingly to plan) and by the third day, the Progress is the same. That means that by the third day the Project has already a delay.
So I would like to know which formula can I use to find out this expected or planned Progress and then I can be able to make a comparison against Progress completed and create alerts if neccesary.
Thanks.
If you create a [Projected % Complete] column, you can enter this formula into it...
=(TODAY() - [Start Date]@row) / ([Scheduled End Date]@row- [Start Date]@row)
This will give you how far into the scheduled time you are for whatever today's date is. You can then build your alerts off of whether your actual % complete is less than, greater than, or equal to where you should be (projected % complete).
To show the projected finish date based off of the current progress and the start date, create a date type column [Projected End Date] and insert this formula...
=[Start Date]@row+ ((((TODAY() - [Start Date]@row) / ([Scheduled End Date]@row - [Start Date]@row)) - [Actual % Complete]@row) * ([Scheduled End Date]@row - [Start Date]@row)) + ([Scheduled End Date]@row - [Start Date]@row)
Thank you!
I have a similar request: I would like to see how the projected end date of a task will impact the overall projected end date of the project taking the predecessor relationships into account. Any ideas on how to do that with a function or in a dashboard?
I've got the following formula in a Check Box column to check when something is due in the Next 3 weeks. =IFERROR(IF(AND(WEEKNUMBER([Projected Cleaning Date]@row ) = WEEKNUMBER(TODAY()) + 3, YEAR([Projected Cleaning Date]@row ) = YEAR(TODAY())), 1), "") I have them for 2 weeks, 3 weeks, 4 weeks, and 5 weeks. These stopped…
I'm using salesforce connector to pull my team's hours information in real-time. The Salesforce connector sheet contains sheet summaries that I'd like to use a cell reference for a different sheet. I can't seem to find the best way or formula to do this. I don't want to use a dashboard with report widgets because I prefer…
I have two formulas which work well independently, but when I combine them they don't. formula 1: =IF(YEAR([Joined date]@row ) = 2025, JOIN(COLLECT({Membership Survey 2025 - Experience}, {Membership Prioritisation Survey 2025 - Org}, [Organisation name]@row ))) formula 2: =IF(YEAR([Joined date]@row ) < 2025,…