Sign in to join the conversation:
Hi, which formula can I use to calculate the expected Progress (depending on the current date)?
Thanks
Could you give more details and share some screenshots?
Hi Paul,
I have the Start Date, End Date, Duration (days) and the Progress given by each responsible. From this Information I would like to calculate the expected Progress, how shall the Project must be going on an specific date.
For example:
I have a Task with 10 days as Duration. by the second day the Progress completed is 20% (that means is running accordingly to plan) and by the third day, the Progress is the same. That means that by the third day the Project has already a delay.
So I would like to know which formula can I use to find out this expected or planned Progress and then I can be able to make a comparison against Progress completed and create alerts if neccesary.
Thanks.
If you create a [Projected % Complete] column, you can enter this formula into it...
=(TODAY() - [Start Date]@row) / ([Scheduled End Date]@row- [Start Date]@row)
This will give you how far into the scheduled time you are for whatever today's date is. You can then build your alerts off of whether your actual % complete is less than, greater than, or equal to where you should be (projected % complete).
To show the projected finish date based off of the current progress and the start date, create a date type column [Projected End Date] and insert this formula...
=[Start Date]@row+ ((((TODAY() - [Start Date]@row) / ([Scheduled End Date]@row - [Start Date]@row)) - [Actual % Complete]@row) * ([Scheduled End Date]@row - [Start Date]@row)) + ([Scheduled End Date]@row - [Start Date]@row)
Thank you!
I have a similar request: I would like to see how the projected end date of a task will impact the overall projected end date of the project taking the predecessor relationships into account. Any ideas on how to do that with a function or in a dashboard?
I am looking for a formula that will look at this table and pull the hours per week based on 2 criteria – group and week. Right now, I have the tables separated so that I can use a vlookup formula. But that means I have to have 5 different formulas, 1 for each group. =IFERROR(VLOOKUP(ROUND(($[First Receive]@row - $[Week 1…
Hi, I am needing to create a column that will display the correct month based off a date in another column. My columns are below. I am not certain on which formula to use. Thanks for the assistance!
My spreadsheet has 4 columns are updated each Month with Stable, Improving, Developing, and Negative. Negative is the highest priortiy, then Developing, then Improving. Please assist with a IF statement, that would look at all 4 columns an update the cell with the highest priority word.example 3 stables and a developing…