Hi everyone,
does anyone have any experience with resource management of people with different availability in a week? As far as I understand, Smartsheet is taking 8hours a day for each resource into consideration.
Thanks for any help.
Pavla
Hello Pavla,
Thanks for your post! It sounds like you're looking for a way to manage resources who have varying availability. Currently, schedules are managed at the sheet level in the project settings, so it isn't possible to assign schedules or availability to specific resources. I've let the product team know about your request and they will consider it for potential future development. You can also submit a Product Enhancement Request using the Quick Link to the right (Submit Product Enhancement Request)
Note: Smartsheet takes 8-hour workdays into consideration by default, but you can change this by right clicking the column headers to select "Edit Project Settings." From the Project Settings, select Working Days > Edit where you'll be able to define the working days, length of day, and holidays. If you change the Length of Day to a different value, this is the value that will be used for duration and allocation (Define Working Days, Non-working Days, and Holidays on a Project)
Tip: If you want to view allocation in hours rather than percentages, insert a Text/Number column called "Hours" and enter the formula =Duration@row * 8 * [% Allocation]@row(Create Efficient Formulas with @cell and @row). This formula will calculate the number of hours per task based on the % Allocation and Duration. Note that if you change the Length of Day in the Project Settings, you'll want to amend the 8 in this formula to match the length of day you specify (Formula Basics)
One way to workaround the inability to set schedules and availability for specific resources would be to create a "Part Time Resource Allocation" sheet. In this sheet, you'll insert a row for each Part Time resource, enter the Start Date and End Date at the earliest and latest dates possible, then enter a % Allocation representing the percent of the 8-hour workday that they're unavailable. For example, if a resource only works 6 hours out of the 8 hour workday, enter their % Allocation on this sheet as 25%.
Additional information about these features can be found here:
I hope this helps!
Kind regards,Isaac JSmartsheet Support
Howdy, I am working on developing a several dashboards for our team, and for whatever reason the widgets I place are multiplying. I have copied/pasted some, but other I have just added I am ending up with dashboards that look like this: When originally I only had the top four items. It has happened on several different…
I am a construction project manager and built sheets that include actual costs for individual tasks, departments and overall project. I update the costs cells as invoices come in by manually calculating then entering in new amount. Ex: Plumbing: week 1 $300, week 2 $250, week 3 $150 = $700. I enter $700 in cell. I'm…
I have multiple items that each have their own statuses and that roll up to "workstreams" or swimlanes. On the dashboard, I would like to show the progress of the items by swimlane without breaking it out into separate widgets for each. This would ideally be a stacked bar where each bar represented the Items and was broken…