Option to create Multiple Parent Roll up functionality? I created for Actual timeline by using Proje

Sara@
Sara@
edited 12/09/19 in Smartsheet Basics

Hi,

Can anyone help me on this.

I have enabled Parent Roll up functionality for Actual timeline  by using project setting as refer to 1st screen shot.

Same way I tried to add duration and timeline for Planned Time line but it is not auto calculating as i notice at single time we can setup parent roll up functionality for single time line functionality as you can see 2nd screen shot

May i know  manual formula to setup auto calculation for planned timeline as well or else any other solution for this

 

Capture.PNG

Screenshot.png

Comments

  • Alejandra
    Alejandra Employee

    Hi Sara,

    It sounds like you want to define multiple duration and predecessor columns in the project settings. If so, there currently isn’t a way to do this, but please feel free to submit this feedback to our Product team directly using the Product Enhancement Request form (you’ll find a link to this here in Community under Quick links on the right).