RYG Balls associated with Dates
jstotler
✭✭
I have search and tried multiple expressions and cant seem to get things to work correctly.
I have columns:
Estimated Start Date
Actual Start Date
Estimated Completion
Current Finish Date
Actual Completion Date
What I would like is the RYG Ball to be blank for any row that does not contain an [actual start date].
Green if [actual completion] has date populated
Yellow if [Today] is within 5 days of [Estimated completion]
Red if Today is past the [Estimated completion]
Any assistance would be greatly appreciated.
Comments
-
Thanks! You helped tremendously.
The only thing that was not working was the yellow ball showing up if the estimated completion was within 5 days of today.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives