Please can someone help me with a way to indicate the conclusion date of a task, automatically?
Once I have a status set as finished, I need the current date to be "locked" on a cell and no changed/updated anymore.
Hi Guilherme,
You would probably need to use a third-party solution like Zapier or similar for this.
A possible workaround could be to lock the row automatically with Alerts & Actions.
Would any of those options work?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
You might consider changing up the process. We started using Actual Start and Actual End date columns to determine whether a project was Not started, In Progress, or complete. We then applied a formula to the Status column and locked it down so that a status couldn't be changed manually and overwrite the formula.
=IF(AND(ISBLANK([Actual Finish]@row), ISBLANK([Actual Start]@row)), "Not Started", IF(ISDATE([Actual Finish]@row), "Complete", IF(ISDATE([Actual Start]@row), "In Progress")))
Hi all - I have a report that includes a symbol column type. The report is displaying the column correctly (with the symbol). However when I create a Dynamic View from this report, instead of that column displaying symbols, it displays text. Is there a way to get symbols to display in Dynamic view?
Does Smartsheet have the capability to create business process flowcharts or process documents? Im looking for something similar to Vizio or lucid chart?
My manager has asked me to put a border around all of my metric widgets in my dashboard. I cannot figure a way to do this. I tried creating a jpg. of an unfilled rectangle and bring in as an image. But I could not get the widgets to stay on top of the reectangle. Any ideas?