Sign in to join the conversation:
I cannot get this formula to work. Any suggestions?
=IF([% Complete]1=0%,"Not Started",IF([% Complete]1=100%,"Completed","In Progress"))
Hi Scott,
Smartsheet looks at the numbers in a column formatted for percentage (for example, a % Complete column) as values between 0 and 1. Use decimal values (examples: 0.25 for 25%, 0.5 for 50%) to get the correct comparison, as opposed to whole numbers.
Try this.
=IF([% Complete]@row = 0; "Not Started"; IF([% Complete]@row = 1; "Completed"; "In Progress"))
The same version but with the below changes for your and others convenience.
=IF([% Complete]@row = 0, "Not Started", IF([% Complete]@row = 1, "Completed", "In Progress"))
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Did it work?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
In my job as a scheduler a common question is "which of the predecessors for this activity is driving the date?" Currently I have to rely on my own knowledge of my schedules or, worst case, I have to look at every predecessor until I find the one I am looking for. Microsoft Project is nice because it has the "inspect"…
Hi! I am trying to create DVs from this sheet that will do the following: In this screenshot example - Elizabeth is the roadmap owner, but Deb is the Calendar invite owner. So in Elizabeth's DV, I still need her to be able to see this row, but not be able to edit the Calendar Update Complete column. In Deb's DV, I need her…
Hi all, Is it possible to display some sort of graphic like this within a dashboard? I'd be taking data from a form and gathering total numbers of of "yes" and "non" questions to get the numerator and denominator for each row or column in the picture. I think I could do the metric sheet part of this task no problem, but…