Sign in to join the conversation:
I cannot get this formula to work. Any suggestions?
=IF([% Complete]1=0%,"Not Started",IF([% Complete]1=100%,"Completed","In Progress"))
Hi Scott,
Smartsheet looks at the numbers in a column formatted for percentage (for example, a % Complete column) as values between 0 and 1. Use decimal values (examples: 0.25 for 25%, 0.5 for 50%) to get the correct comparison, as opposed to whole numbers.
Try this.
=IF([% Complete]@row = 0; "Not Started"; IF([% Complete]@row = 1; "Completed"; "In Progress"))
The same version but with the below changes for your and others convenience.
=IF([% Complete]@row = 0, "Not Started", IF([% Complete]@row = 1, "Completed", "In Progress"))
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Did it work?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hello , I am looking for help to write a formula that will check a box if certain criteria are met. I have students that are signing up for a class and they need the previous class or classes as prerequisites. for example i have class 1, class 2 , class 3 and class 4. each higher number class needs to have completed the…
Hello, I am looking for formula help where I want to return the earliest date in a range for different workstreams groups on a project. The source sheet is formatted as a date field, and the formula used below is returning a 0 no matter what I do. Any suggestions? =MIN(COLLECT({Project Plan - start date}, {Project Plan…
I currently have 14 sheets with the following columns: Batch # and Reviewer I use an Index Distinct formula to acquire the unique batch numbers from all 14 sheets and put them into 14 columns on the 'metrics' sheet. I then use another index distinct to get a list of all the unique batch numbers into one 'Unique Batch…