I am using predecessors in my spreadsheet and need some assistance with lag times.
For example, one task is to sign the contract with the meeting planners (we do that in November)--that's line 12 in my sheet. Our first payment is not due to the planners until June of the following year. If I put line 12 in as the predecessor for the first payment, Smartsheet changes the dates of the payment due. I have to play with it quite a bit to get the right lag time recorded. Any help appreciated.
Thanks so much!
Lainie