Only Show Tasks with Completed Predecessors in Report

chad.jackson73431
chad.jackson73431 ✭✭
edited 12/09/19 in Smartsheet Basics

Hey folks. We have a number of projects with the right dependencies set up. We have reports for all our people to use. However, they're seeing tasks before those task's predecessors are complete. That's causing them to start tasks before the tasks are ready to be started.

Is there a way to only show tasks with predecessors that have been completed or that have no predecessors?

Under the 'What' option in the Report Builder, I found the option to include Predecessors, but do I specify it 'contains' a *? Advice would be greatly appreciated.

Tags:

Comments