I have some update requests triggered to send to an email in a contact column after a symbol column becomes starred, which is based off of a formula. I have that column turn to a star after it's been 4 days since the date in the "Week Of" column. The dates in that column are always Sundays, and I want the star column to be clicked and send out an update request once Friday hits, so 12am Friday. I actually have the update request sent at a 1 hour delay, so they should go out at around 1am. See screenshot below for details on the formula.
This has worked the past 2 weeks. This week for some reason, my update requests were sent out three times- at 1:48am, 6:48am, and 10:48am.
Anyone have an idea why? Does it have something to do with my formula?