Different working days per task

jd Runnion
edited 12/09/19 in Archived 2015 Posts

New smartsheet user here.  I really like it!  

 

However, I need a way to change working days on a task level.  Is this possible?

 

For example, I have  "cure time" for concrete finish work.  The time is continuous regardless of holidays and non-working days.  The concrete just sits and cures.  Nothing else needs to happen.  Unfortunately, if cure time lands on a holiday, the gnatt chart will show one additional day.  If I then change the "duration" to account for the holiday, I wind up having to recheck it each and every time a predessor is modified.  This is tedious and dangerous in my line of work.  

 

Seems like there should be a simple fix? Is there?

 

Other than that, so far it's awesome.