Flag as At Risk if Due Date in Past and Complete = X
mmac
✭✭✭✭✭
Hello, I'm looking for support on what formula to include in the Flag symbol column that would act against the following:
If Due Date is in the past and Complete = X (Visual Symbol), then flag At Risk column with Red flag
Currently, using formula below to flag At Risk column with Red flag based on requested due date column.
=IF([Requested Due Date]1 < TODAY(), 1, 0)
Tags:
Comments
-
Try this - assuming X is the indicator you are using.
=IF(AND([Requested Due Date]@row < TODAY(),Complete@row = "X"), 1, 0)
-
Thank you! That worked perfectly.
-
Great! You're welcome. Glad I could be of assistance.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 146 Just for fun
- 63 Community Job Board
- 465 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!