Sign in to join the conversation:
Hi!
I have two columns. One if the Due Date and the other is the Completed Date. I would like to set-up an equation where it counts the number of times an item was completed late (after the due date). Is this possible? If yes, what is the equation?
Hmmm. I swear I know a better way of doing this, but I am having trouble getting anything to work. To do this quickly, you could create a helper column and use the following IF statement =IF([Completed Date]@row > [Due Date]@row, "late")
That will write the word late in the row... then you could do a simple... =Countifs([Helper Column]:[Helper Column], "late")
You could do this with the followting equation:
=IF([Completed Date]3 > [Due Date]3, 1, "")
This will put a 1 in the column if the Completed Date was after the Due Date. Then sum the column.
Here is an example sheet https://app.smartsheet.com/b/publish?EQBCT=d3c78d81b9424434a84055dfa1e2f28d
Comparing two (or more) columns for a count at the row level without a helper column is possible with an absurd amount of nested COLLECT functions which also happens to be rather inflexible and easily broken.
I have tested and dug through the forums here and tested some more, and the best thing by far I personally have found has been to use a helper column to compare the cells at the row level and then count the helper column.
If you can find a different way, I'm all ears. Adding extra stuff in after a sheet has been in use enough to have a few thousand rows is rather tiresome.
Hi All, I just want to pull the title 'BSR Tracker' in column 33 Please note there's another Blue bar in the same tracker i.e. two levels at ancestor = 0 so i just want to pull that title in. currently the formula im using but doesn't seem to be working is: =IF(COUNT(ANCESTORS([Site Name]@row)) = 0, "",…
Dear Smart Community, I am experiencing an issue with a specific email ID that is not receiving notifications triggered through workflow automation. However, the user is able to receive emails when I send an update request manually. I have tested several scenarios in coordination with the IT team. For example, when…
Hi! I have a formula that indicates the number of days since the last update. I have 2 different projects that were updated on the same day, but one is showing 1 day since the last update and one shows -1 since last update. The only difference is that the 2nd one was submitted after 5 pm Pacific Time. It's not possible to…